Green Building: Can You Get a Construction Bond?

This post was originally posted at NWConstructionLawyers.com, our sister blog. Check out the original posting over there.

 

A bright new topic surfaced on one of our favorite construction law blogs today and we thought we would continue the discussion over here at ConstructionLawMonitor.com.

Construction Law Musings is a construction law blog focusing on Virginia law. The site is managed and edited by super prodigy Christopher Hill, one of the most inciteful and engaging construction law attorneys on the web. Check out his twitter and his blog for great construction law news and information.

Musings has a Guest Post Friday section wherein people from the nationwide construction world are plucked to post their incite on the construction world. Wolfe Law's Doug Reiser and Scott Wolfe have each been given the honor to post on Guest Post Friday in the past.

This Friday, Kevin Kaiser, of Surety Bond Education Center and the Surety Bond Insider, was Chris' guest. Kevin stopped by to comment on the growing concerns apparent in the bonding industry, resulting from a boom in green construction.

Kevin's article shows that the majority of sureties are frightened by increased liability for performance standards in LEED (and other) green construction. Do sureties provide performance bonding for post-construction energy performance? Are sureties assessing the inherent risks of green construction in writing bonds?

Kevin discusses that change is coming. Recent policy changes by top surety organizations are seeking to eliminate the Green Building Act's "performance bond," by changing the requirement to simply require a "bond." Whatever that means is still up in the air, and green building expert Chris Cheatham correctly points out that the availability of these bonds is still an unsolved mystery.

In any event, surety companies are going to have to meet this challenge head on. Green building has infiltrated almost every community, due to federal and state mandates to utilize sustainable building practices on public works. Soon enough, nationwide private construction will be rife energy performance standards (if not already). Sureties will have to meet the goals of these projects and provide suitable bonds.

Continue with the debate over at Construction Law Musings. We commented, so can you. Let your opinion be heard.

Washington & Oregon Federal Projects: Bidding, Wages and Miller Act Rights for General Contractors

Federal projects are on the up and up. We know this because there was a Recovery Act and Stimulus Plan - and certainly this money did not disappear. Money was dumped into the hands of various federal departments to develop facilities and spur the new New Deal. 

Recently, there has been a rash of federal projects sprawling across Washington and Oregon. In Washington, we see several naval and coast guard projects. The same can be said down in Oregon, where federal administration buildings are getting a green makeover.

The general contractor - or prime contractor - is an interesting animal. The project starts and ends with this entity's proposal, planning, work, and clean up. A prime contractor withstands the most intrusive and strenuous of all procedures in trying to obtain federal work - but oh what a sweet reward for the contractor who does a job well.

But, can your firm get this work? If it does get this work, how does it manage its obligations and be sure that it gets paid?

This article series covers Bidding, Managing Labor & Wages and Making Claims under the Miller Act. We will address these items for the prime contractor - and in the near future, we will revisit for you subcontractors and suppliers. Prime contractors should also pay close attention to that second series, to better understand the needs of their subcontractors and suppliers. But for now - a Prime's bidding:

Bidding a Federal Project

Well, there is no secret to obtaining federal projects. Work is bid similarly to the manner in which state projects are bid: projects are awarded to lowest responsible bidder.

If you are a general contractor or project developer, this can be tricky, but its not an impossible science. Register appropriately and follow the forms issued with project specifications.  

Follow these basic steps when readying yourself for a federal project:

 

  • Register

You need to register with the Central Contractor Registry (CCR) in order to bid on most jobs. You can visit the site at this link in order to begin the process. The process is simple and will streamline your bidding process.

Secondly, register with Federal Business Opportunities (FedBizOpps) in order to access most listings and documents. This is also where most government agencies, such as General Services, Army Corps, Commerce, Interior, and Veterans, all issue their contract announcements and bid specifications.

Luckily, registration is simplified by the mighty world wide web. Remember that there are several other resources to government contracts, such as GovernmentBids.com, AcqNet, and ConstructionWebLinks.com.

 

  • Familiarize Yourself with the Forms & Obligations

There is no single standard form. Each organization utilizes different contracting forms, though much of the terminology and practice is similar. But, by simply perusing the FedBizOpps.com website and briefly reviewing contract solicitation forms, you can inspect project documents and begin to becme acquainted with their requirements.

For instance, the US Army Corps of Engineers has a tree removal project for the famous Hiram Chittenden Locks. The project's listing is located here, which includes a link to the contract solicitation documents at the Army website here.

Reviewing this smaller project's documents illustrates the common bid package, complete with a solicitation/bid form, drawings of the project area, schedule of values, and the terms and conditions of the work and bidding. You might want to pay close attention to #4 on the Instruction sheet, which says you must be registered with the CCR or do not bid - because you are not getting the job.

Also, the Miller Act requires all projects that cost $100,000.00 or more to be bonded by performance and payment bond. It is helpful to have a continuing guaranty agreement with a surety so that you can streamline the acquisition of a bond and be ready to bid without a moment's notice. Consult you insurer or surety to find a better way to secure your work.

Taking the time to "faux-bid" a few jobs will help you be ready for the big day when an attractive project shows up and you MUST bid. Get it right the first time and avoid costly litigious fights over contracting awards.

 

  • Get an Attorney

I am a bit conflicted here - because I am an attorney. But, I cannot stress the importance of being cautious and consulting with a construction attorney. A good public contracting attorney can review your completed bid submissions for errors and ensure compliance.

You need to be aware that simple errors on forms might kill your right to a contract award. Clerical errors such as improperly executed corporate resolutions might lead to a grizzly battle with second place finishers. More often than not, if you have failed to meet strict standards of acceptability - you will lose your contract. 

Remember, you may invest thousands of dollars in bidding on a federal project. You can easily justify the cost of attorneys fees in your bidding allowance, especially when you run the risk of losing millions in revenue.

Take your time, pass it by your counsel and bid timely. 

Stay tuned for the second installment this week. We will be discussing the application of the Davis-Bacon Act, compliance with OSHA and the management of your subcontractor's workers.

 

 

Scott Wolfe Contributes Guest Post on Construction Law Musings

Big thank you to our friend Christopher Hill who operates the Construction Law Musings blog for allowing me to become his blog's first three-time Guest Post Friday writer.

This morning, Musing's published a blog post I wrote titled "A Lien By Any Other Name Can Sound Just As Sweet."  

The article provides readers with a broad overview of the lien-like remedies available to them, as they differ based upon the classes of projects. In large part, the article explains the difference between a traditional lien (filed against the property on private projects) and a "claim" type of lien (filed against a bond on a state and federal project).

Of course, this post only skims the surface, but sometimes, it's the basic information that is needed to help folks understand the details. And why is it important to understand these details? The article on Musings concludes with that answer as follows:

Regardless of what class of project you’re working on, a lien-like remedy is probably available to you in the event of non-payment. However, it’s critical to understand the different remedies available at the onset of construction, for each remedy carries different pre-lien or pre-claim requirements.

Take a look at the article by clicking him, and be sure to subscribe to Christopher's blog which posts great information relevant to those in the construction industry.

Introducing Two New Blogs Focused on the Pacific Northwest

Wolfe Law Group is happy to announce the launch two new blog focused on the Pacific Northwest, and particularly the states of Washington and Oregon.

The Northwest Construction Law Blog focuses on construction law issues and updates in Oregon and Washington.  We launched this blog to help your company stay informed about important legal updates in Oregon and Washington, but also to educate contractors and suppliers about legal issues they confront (sometimes unknowingly) everyday

At the Northwest Green Building Law Blog, we’ll be focusing on green building legal matters that affect the states of Washington and Oregon.

Wolfe Law Group practices law in Washington and Oregon, and focuses its practice on the construction industry. We have two full-time LEED AP attorneys who are familiar with green building issues and disputes.

Wolfe Law Group is the leader in the legal industry with its publishing of quality legal resources and information. All of our attorneys consistently publish articles and discussions on our legal blogs, and all of our content keeps you in mind. We strive to post articles and discussions that are relevant to your business, so you can stay advised of legal matters that are important to your company, and get a better all-around understanding of how the law affects your day-to-day work.

Take a look at our listing of industry leading blogs here.

Organization: A Secret To Managing Legal Messes...Start 2010 on the Right Foot

Happy New Year.  

Did you make it through 2009 alive?  It certainly was a tough year.  Perhaps your legal bills were more than ever before, or maybe you got by without spending much or anything at all on counsel.   In either case, let's make a resolution to avoid expensive legal bills in 2010.  

How do you do it?

Ask an attorney how to avoid legal messes and expensive litigation, and they'll likely start discussing legal precedent, contractual provisions and other technicalities.   Sure, all of that stuff is important when you're knee deep in litigation.  By that point, however, you'll already have an attorney to handle those issues.

What about before you're knee deep in litigation; how do you avoid legal messes?  

The most valuable piece of advice I give clients who ask me how to avoid legal fights and messes is to be organized

Organization is your best friend when entering a litigation scenario.   It proves your case when you're right, and it paints a clear picture of your risk and exposure when your wrong or possibly wrong.   And insofar as your contractual and legal duties are concerned, if you're organized and know what they are, you'll have a much better chance of fulfilling them.

Now, you're quite lucky that it's now 2010.   That's because the World Wide Web has been improving for over 20 years now, and it's got a million ways to help you organize your construction business (large or small) in the new year.    

Here are a few of our favorite web applications out there that can help you stay organized, and avoid legal bills and messes.

Keep Your Files Organized

Construction projects can have tons of paper exchanged.   Contract documents, job specs, change orders, correspondence...the list can go on.   And, to top it off, all these documents are being exchanged between you and your employees, and your subcontractors, suppliers, their subs and suppliers, the property owner...the list can go on.

How do you manage all that collaboration, and all that paper?

SugarSync:  This works with PCs, Macs, on iPhones and Blackberrys, on just about anything else...and it's easy as pie.   Add a file to a folder on your computer, and it instantly gets added to that folder on everyone else's computers.  You can share files or folders with other companies, allowing them to just see the docs or edit / trash it.

The possibilities are endless, and the cost is low.  This program can single-handely change the way you exchange documents on your construction project.

Box.Net:  Like Sugar Sync, this is another document management system to help you organize documents to a construction project and collaborate with others on the documents.  Insofar as features and collaboration are concerned, Box.net gets the edge.  You can sign documents electronically, send documents via fax, edit docs, send docs via postal mail, and more...all within the box.net interface.   Box.net is entirely web-based, however, meaning you can't just drag and drop a file into a folder on your PC and let it do its magic.  On the ease of use, SugarSync gets the edge.

Notice and Lien Deadline Management

It doesn't matter if you just work in one state, or if you work in every state.  Notice and lien requirements are confusing, and the effort required to comply with these requirements can feel constant.   How do you keep up?

ExpressLien:  Enter Express Lien.   This company provides two different sets of services. 

First, it helps you manage your lien and notice requirements and deadlines.   You put in your project data, and it calculates your requirements and deadlines and displays it to you all on an easy to read online interface.    How much?  It's free.

Second, if you want, you can order your notice and lien documents directly through Express Lien.   They will take your project data, create the documents, file/send them, and keep track of all the delivery and filing data in your online profile.   Document filing is done for a low flat fee.

Will The Health Care Bill Hurt Small Contractors?

At the eleventh hour, the U.S. Senate added a provision to the controversial health care bill pending in Congress that has the construction industry on edge.    The Associated General Contractors of America released a statement on their website complaining that "without debate or advance notice, language was added to the Senate health care legislation that singles out small construction firms for harsher treatment than any other industry."

What is the rub?

Well, while employers with less than 50 employees are typically not required to provide health care coverage, the exemption for construction firms is only those with less than 5 employees!   Failing to provide health care coverage could subject the construction firm to fines.

The Wall Street Journal is running a great article about the construction industry's reaction to the recent addition to the Senate bill.  

Contractors Beware - Louisiana Appeal Court Says Compliance with Building Codes is Not a Cause for Change Orders

This fall, the Louisiana 1st Circuit decided Bonvillain Builders LLC v. Gentile, finding that a property owner was not required to pay nearly $50,000 in requested change orders because the extra work was required under the original contract.

In Gentile, the construction contract required the contractor to meet all prevailing building codes. A situation arose with regard to the parish's drainage requirements, as the original design did not accommodate the code. The drainage study and total completed price for the drainage work was eventually tallied to cost $47k more than estimated.

The contractor wanted the property owner to pay for this, because it was an "unknown condition." The owner rejected the change orders arguing the contractor was responsible to meet prevailing building codes.

The Gentile court agreed with the property owner. According to the first circuit, the contract unambiguously required the contractor to comply with prevailing building codes. The fact that the designer and the contractor overlooked the drainage requirements and failed to properly provide for the the same in its plans and bid…did not pass the burden of paying for the drainage onto the owner. Instead, the contractor/designer was liable for the mistake.

The court found that the drainage requirements were not a "hidden condition" of the property, but merely, something the contractor and designer overlooked.

What Does It Mean For You?
Nearly every construction contract has a provision similar to the one in Gentile where the contractor (or sub) is required to meet prevailing building codes. When bidding on a project, its critical to bid responsibly. Failing to understand and accommodate the prevailing building codes applicable to the site can end up destroying the project's bottom line.

The real key is understanding what is and what is not a "change order." The term gets used so frequently by those working on a construction project, we sometimes forget its true meaning and warp the term to work to a party's convenience.

A change order is not issued overtime the cost of work or scope of work is greater than anticipated. It's only issued when the scope of work is changed.

If the owner adds a new complex to the plans, or requires a different quality of materials - this will likely result in a change order. However, if you simply didn't correctly estimate the amount of work that would be required for a task or misunderstood the prevailing building codes…a change order will not be an available remedy.

Like the situation in Gentile, you will be legally responsible for your own mistake.

Of course, this Gentile case will not likely apply to a scenario where a change is required because of a hidden site condition. If a hidden site condition is found, a change order is appropriate. The court in Gentile just clarified something that may seem a bit obvious: failing to take into account the building codes in the parish was not a hidden condition, regardless of whether it was or was not scoped in the original plans.

Green Building Contracts: ConsensusDOCS New Release, A Solution?

As green building has gained steam, so has the discussion over the legal implications of a new construction process, which relies heavily on performance during and after construction.

The US Green Building Counsel's LEED program rates the environmental performance of a construction project. Using several international building standards, the LEED program provides credits and certification of buildings, so that projects obtain funding and are generally more attractive as a sustainable and potentially low-cost energy alternative.

Those of you aware of the LEED certification credits, likely understand that there is in inherent problem in controlling for the risk that a project will not perform as intended. Therein lays the problem: if the intention of the project is to perform, how can try to contractually release or alleviate a contractor's liability for non-performance.

For the past several years, construction attorneys (like us at Wolfe Law) have carefully drafted their own sets of construction contract documents, which seek to fairly allocate risk of non-performance.

Until now, no standard set of contract documents had been released by the Architect's Institute of America (AIA) or ConsensusDOCS, the two leading contract document developers. 

On November 11, 2009, ConsensusDOCS released "ConsensusDOCS 310 Green Building Addendum." ConsensusDOCS is a mixing pot of several construction industry interests, including builders, designers, developers, and sureties. Over time, they have become the AIA's chief rival in designing contracts to be used on both commercial and residential projects.

The new addendum is discussed in a recent article by Architectural Record's Scott Blair, who quoted executive director Brian M. Perlberg:

“'ConsensusDOCS 310 Green Building Addendum,' released on November 11, is intended to define, clarify, and establish the relative roles and responsibilities needed to successfully deliver a green-building project." 

"Perlberg says the drafters 'made a very conscious effort to make the document neutral.' While it's likely the majority of users will be seeking LEED certification, it is designed to work with other third-party certifications or when an owner wants to meet its own independent green goals."

We truly hope that this document assists in clarifying the allocation of risk of non-performance. As we try to get our hands on this document, we turn to the ConsensusDOCS website to get a more in-depth view at the drafters' intentions. 

The ConsensusDOCS website provides the following:

"Another industry first – appropriate for use on projects with green building elements, particularly those seeking a third-party green building rating certification such as LEED. It provides a contractual mechanism to identify clear objectives, and assign roles and responsibilities to achieve green goals. The parties designate a Green Building Facilitator (GBF) to coordinate or implement identified objectives, which can be a project participant or consultant. It contemplates that such services will be included in the underlying agreement with the project participant or in a separate agreement with a GBF."

ConsensusDOCS also published a written handbook, explaining each of the contract addendum's Articles. The structure seems to have a more generalized approach, allowing the parties to select particular performance parameters consistent with the project goals. 

At first glance, the addendum seems to be a very basic framework, which permits the contracting parties to fill in many gaps. 

Article 3 lays out the project's goals and procedures. The Article also contemplates the selection of a particular rating system, the methods of attaining those ratings, and timelines.

Article 4 create a "Green Building Facilitator," (GBF) whom seemingly has a role similar to that of a construction manager. The GBF is entrusted with facilitating the relationship between designers and contractors, while ensuring that the proper documentation is submitted to attain accreditation. 

Article 6 incorporates the particular "green measures" that are to make up a portion of the design and construction work to be completed on the project. In effect, this portion of the addendum adds to the overall job scope. The Article further provides mechanisms which assist project participants in handling conflicts between "green measures" and the original scope of services.

Under Article 6, the contract clearly indicates that the architect will remain responsible for incorporating "green measures" in to the job scope. The GBF helps to facilitate the architect's plan and the contractor's building process.

And then, we get to what we were hoping to see: risk allocation. Article 8 discusses liability and risk, and who and when a party might be liable. 

One absolutely necessary provision was the waiver of an architect's or a contractor's liability for "defects or deficiencies inherent in the elected green measures as they affect their ability to achieve the elected green status."

Another provision handles consequential damages that are incurred by a project owner, when the project does not meet green standards. This allows the parties to determine whether or not these types of damages would be waived under a typical consequential damages waiver, or be subject to liquid damages, or otherwise.

Finally, the Article address the GBF's liability in managing the goals of the project. It appears that the addendum leaves this liability to contracting parties.

In sum, the addendum seems to brush over the major topics, while leaving day-to-day project management and performance to the agreement of the parties. The ConsensusDOCS addendum appears to be a good first step in controlling green building liability, but we are certain that the agreement will be (and should be) persistently tweaked and bulked up in the coming year.

Contract Drafting: Dispute Resolution Tactics of Importance

A good contractor has a plan about how its problems will be resolved. A good contract is the first step to ensuring you have a protocol for handling the claims of your customers and your problems with your subcontractors and vendors.

In the past it was simple, choose a governing law and a forum - hope for the best. Nowadays, contractors are provided with a multitude of options, some binding and some suggestive. But, in any event there are several mechanisms that allow you as a contractor to set an operating procedure for dealing with potentially damaging legal disputes.

In turn, and briefly, we want to discuss some of the terms that might be helpful to you as a contractor:

Claims Periods

As long as they are reasonable and fair, contractors can set claims periods within which their customer or subcontractor must raise an issue that it believes may lead to damages, back charges, or other credits.

A claim period is exactly what is says it is: a period of time to make a claim. The theory is simple, if you learn (or should have learned) of an issue which leads to a claim of damages, you must raise it within a certain amount of time. If the claim is not raised timely, it is barred by agreement.

In order to have an effective clause, you must solve these problems:

(1) What is a claim? How do we define a claim?

(2) When does the claimant learn of the claim, or when should it learn of a claim?

(3) What is a reasonable amount of time to make notice of the claim?

(4) What is the most efficient means of making notice of the claim?

A notice clause is extremely helpful with regard to claims for additional compensation, changes in the work and delays on the project.

Liquidated Damages

One of the most important items to resolve in a contract is the methodology you will use to calculate damages. Eliminating speculative calculation methods is vital to streamlining dispute resolution.

In the case of delays and overruns - liquid damages (LDs) is a very useful tool. LDs are used to stipulate to a specific amount of damages per time unit. Both parties will agree to this damage as fair and reasonable prior to beginning work on the project.

An example would be a daily LD for project overruns. This is not only useful for the project owner, but also for the contractor, as it can now predict amounts that will be back charged against it.

A useful LD clause will be coupled with an effective change order provision which allows the contractor to extend the time for completion, in order to avoid LDs. But the clause is effective for all parties involved and reduces the need for speculation and protracted dispute resolution.

Records Maintenance

Often the largest challenge in resolving a dispute is locating documentation and then shuffling through papers. We would advise that you reduce this burden by requiring an affirmative duty to maintain and routinely produce documentation.

A clause which obligates your customer or subcontractor to provide weekly or monthly production of logs, time sheets, applications for payment, change orders, invoices, receipts, etc. - will drastically reduce the length and costs of your dispute resolution.

Furthermore, the obligation should be affirmative, thus limiting your customer's or subcontractor's ability to raise a claim or defense based upon an unknown fact which is not documented (i.e. change order or alternative agreement).

Dispute Resolution Methods

There are various dispute resolution options available these days. Mediation, Arbitration and Litigation are all possibilities which might be attractive to you and your business. There are various outfits that can provide the alternative dispute resolution that you might want.

First off - the American Arbitration Association is not the only mediation and arbitration body on the market. In fact, due to their high costs, slow dockets and excess administration, they might not be the right choice for you. Alternatives, such as the Metairie, Louisiana outfit, ADR, Inc., provide more streamlined, expedited and cost-effective options.

There are also individuals who provide their services through their own individual companies. If you are in Washington state, one such option is Christopher J. Soelling, PLLC. Mr. Soelling is highly productive mediator who does a wonderful job of meeting the needs of adverse parties, assuaging those needs and finding an acceptable compromise.

Whatever your choice, you need to control it in your contracts. Mediation, Arbitration, and Litigation might be used singularly or in conjunction with one another. A contractor might wish to utilize non-binding mediation for pre-termination disputes while the work is on-going, but elect for arbitration for post-termination disputes.

You may also want to reserve the option to select your forum after a dispute arises. In some cases, a contractor's cleverly drafted contract might obligate a party to bring an action before a court of law, but reserve the contractor's right to remove that action to arbitration, if it so elects. Whatever your choice - make certain that you understand your protocol and plan accordingly.

Stipulations for Alternative Proceedings

When a party utilizes litigation as a dispute resolution tool, the rules are set by the courts. Alternative dispute methods such as mediation and arbitration have some simple rules, but much is left to the determination of the parties and the arbitrator or mediator.

It is very helpful to think about your litigious needs beforehand and stipulate to some safeguards in your contract.

One of vital importance is the level of discovery you want to allow. In most cases, you will not be provided with the right to proceed with depositions and advanced discovery in an arbitration. If you foresee the need to obtain admissions, interrogatories (questions with written answers) or production of documents - stipulate to the same in your contract. If you think that you will need to obtain the deposition of parties - elect to permit that examination in your contract. 

The costs and fees and methods of paying those fees, should also be a concern. Generally, the claimant is required to front fees and costs. You might want to obtain an agreement that both parties will split costs, pay up front and be entitled to recoup those fees if they are successful.

Fee and Costs

By now this should be a staple in your contract - recovery of fees and costs. But how much? 

Every contract should have a clause which provides you with recovery of your fees and costs in the event that you are successful in your claim. But, contracts often do not define the extent of those fees and costs.

You may want to stipulate to a liquidated damage of a certain percentage of the recovery (say 25% of the damages awarded) or, if you want to cover all bases, you might want to define the time period and types of fees and costs that are recoverable. For instance, a contractor can elect to recover all fees incurred since the date notice of the claim was made, including in house attorney time, collection agency costs, and attorney fees and expenses. 

However you seek to recoup these losses - this clause is vital.

Review and Appeal

One of the major reasons that people and entities are detracted from alternative dispute resolution is because of the binding nature of arbitration awards without the benefit of appeal or review. 

One way to fax this problem is to provide for a direct and immediate appeal of any arbitration award to the applicable court of appeals. A clause should limit appeals to matters of law, which is a permissible and appealable issue.

Contracts are vital to the success of a contractor. It is important to think ahead and limit your exposure to difficult, costly and lengthy proceedings. Contact your attorney and iron out your contracts.

Scott Wolfe Jr Speaks at Louisiana Engineering Soceity Meeting

November 18, 2009- Scott Wolfe, Jr., founder and member of Wolfe Law Group, LLC was invited to speak at the Louisiana Engineering Society: New Orleans Chapter's Monthly Meeting.  Scott would like to extend his thanks to the LES for the invitation to speak and the opportunity to meet several people in the engineering industry.

The LES has three main chapters in the state of Louisiana and is dedicated to the advancement of the engineering profession by pursing an active leadership role through various resources. 

For LES' full mission and vision statements, click here.  Incorporating speakers during the monthly meetings is just one of the many ways the LES provides its members with resources and information relevant to the field of engineering.

As a construction lawyer, Scott Wolfe consults with engineers as experts on various cases. Since the discovery of Chinese Drywall in completed construction projects across the state, he has become familiar with the basic problems of Chinese Drywall, how it effects individuals and contractors and how to proceed in the case that Chinese Drywall is detected.

The issue of Chinese Drywall is not only relevant to contractors and home/property owners, it extends to architects, engineers and attorneys.  Engineers in particular are being contracted to perform inspections of homes and businesses suspected of harboring Chinese Drywall.

Scott focused his presentation on the pertinent issue of Chinese Drywall in the state of Louisiana. Below is the slide presentation that was used during the meeting yesterday.