Step-By-Step Guide to Filing Miller Act Claims at Avvo.com

Step-By-Step Guide to Filing Miller Act Claims at Avvo.com

On March 9, 2010 Author By Scott Wolfe Jr

In today’s economic climate, even contractors who typically work on private projects are testing the waters with federal and state construction works.  And unfortunately, these newcomers are finding themselves a bit lost in procedures when it comes time to get paid.

In the event a federal project (or GC on a federal project) goes sour, contractors and materials suppliers must turn to the Miller Act as a remedy.

We talk about Miller Act Claims on this blog here and there, but there are some other great resources out there on the topic.  Take a look at the Miller Act conversations on the Construction Lien Blog or the Federal Construction Contracting Blog for example.

In addition to these resources, I’ve just published a Legal Guide on Avvo.com titled “How to File A Mechanics Lien.”

It breaks down the process in four steps, easy on the eyes:

  1. Determine if you have the right to file a claim
  2. Send Miller Act Notice to the prime contractor within 90 days from last furnishing labor/materials
  3. Sent Notice to the surety (optional)
  4. File Suit Against the Bond within 1 year from last furnishing labor/materials

Take a look at it over on Avvo.com by clicking here.