Posts Tagged ‘Pay If Paid’

Common Law Analysis – Pay-if-paid, Pay-when-paid & Liquidating Agreements in Construction Contracts

In a recent decision, Sloan & Company v. Liberty Mutual Insurance Company (“Sloan”), the US Court of Appeals for the Third Circuit has an in depth discussion regarding some technical yet very important clauses found within many construction contracts between general contractor, subcontractors, owner and the surety. Although the court interprets Pennsylvania law, these concepts are good to know for any jurisdiction.

Pay-If-Paid & Pay-When-Paid

The pay-if-paid discussion starts on page 9 and is defined as “a subcontractor gets paid by the general contractor only if the owner pays the general contractor for that subcontractor’s work.” The court goes on to next define pay-when-paid in contrast to the pay-if-paid. “[A] pay-when-paid clause does not establish a condition precedent, but merely creates a timing mechanism for the general contractor’s payment to the subcontractor.”

The basic difference here is pay-if-paid may never happen if the the owner does not pay the general contractor for the work performed by the subcontractor, in theory. But the pay-when-paid acts more as a timing mechanism for the general contractor to pay the subcontractor, regardless of what the owner has paid for.

Generally courts will look to the four corners of the contract between the parties to determine which way to interpret the meaning of the clause. The interesting part of this holding and a common practice in construction contracts is a clause which modifies the pay-if-paid clause to become a pay-when-paid and this was done here by eliminating the condition precedent after a stipulated amount of time.There are many reasons why this may be done but typically many subcontractors will not agree to an absolute pay-if-paid clause, as the end result can place too much of the risk of loss on the subcontractor. Click here for Daniel S. Brennan’s The Construction Contracts Book.

Liquidating Agreement

Another technical term that is not often discussed in construction, yet is present in many construction contracts is the mechanism know as a “liquidating agreement” Sloan pg 16. The Sloan court defines a liquidating agreement clause as a “process by which a general contractor may assert the claims of its subcontractors against the owner.” This is similar to subrogation in the insurance context. Do not confuse a liquidating agreement with liquidated damages. A liquidating agreement clause can act like a lien, in that it gives causes of action to the subcontractor against the owner where there is no privy of contract. Sloan pg 17.

“Liquidating agreements that enable pass-through claims, such as the one in the contract before us, can also serve to limit the subcontractor’s damages to the amount the contractor recovers from the owner. See Carl A. Calvert & Carl F. Ingwalson, Jr., Pass Through Claims and Liquidation Agreements, Constr. Lawyer, Oct. 1998, at 32, 33.Sloan pg 18.

Conclusion

The end result here, is that typically the general contractor bears the risk of loss when the owner does not pay up, but they can use contractual mechanisms to lower that risk and allocate some of it to the subcontractors. Liquidating agreements and pay-if-paid/pay-when-paid clauses, carefully negotiated at the contract phase of construction projects can lead to limiting liability at the end of a project when things do no go as planned. In the Sloan holding, the general contractor did not bear all of the loss but was forced to pay its subs in a proportional manner to the work performed, keeping nothing for itself. Sloan pg 20. Prevent this from happening to your construction company by working through these clauses when forming your next contract.

Further reading: California Pay-if-paid Wm. R. Clarke v. Safeco Insurance (distinguished by other jurisdictions); Pay-when-paid. A google search of these terms will provide a wealth of information. Always consult with an attorney before negotiating contracts in the construction industry no matter how large or small the project.

Posted in:     Construction Contracts, Construction News, Damages, Federal, Insurance, Litigation, Payment Requirements, State & Federal Contracting  /  Tags: , , ,   /   1 Comment

A Catch-22: Pay When Paid Clauses Do Not Extend the Lien Period

If you search “Pay When Paid Clauses” in Google, you’re going to get a lot of results that say a lot different things. This contractual provision – used in almost every general / sub construction contract – is perhaps one of the most confusing or misunderstood provisions out there.

We recently blogged about the dangers of using one contract in multiple states. The post used the “pay when paid” provision as an example of why multi-state contracts are problematic.

The provision itself seems pretty clear: one party will get paid when the other party gets paid. It isn’t. Interpretation of this provision varies by state, with some states striking down the provision entirely as against “public policy” and other states distinguishing between “pay when paid” provisions and “pay if paid” provisions. The only way to protect your company against this tricky provision is to consult with an attorney about how these provisions are treated in your jurisdiction.

While interpretation of “pay when paid” provisions differ from state-to-state, there does appear to be one constant about this provision across the country: It doesn’t extend your lien period.

Most states require liens be filed within a certain period after you last worked on the project, or after the project is complete. The fact that you or your company is waiting for payment because the prime or an upper-tiered sub hasn’t been paid is completely irrelevant. The lien period still starts when it starts, and ends when it ends.

As you might imagine, this presents a bit of a Catch-22.

On the one hand, you must file a lien to preserve your right to lien. On the other hand, filing a lien may complicate the payment problems for the prime or upper tier sub (and thus your payment problem), and may cause animosity when negotiations are otherwise calm.

Unfortunately, there is no easy fix for this complication. Each situation should be examined individually, and sometimes, a simple joint check agreement may be the solution. It’s just important to remember that good faith negotiations and waiting for payment under a contractual obligation to do so will not likely extend the lien period, and too much talk could result in the loss of lien rights.

Here are some great resources and articles on Pay When Paid provisions:

- Fourth Circuit Concludes Pay When Paid Clause is Unambiguous and Enforceable

- Pay When Paid or Pay If Paid Provisions

- Is Your Pay When Paid Clause Worthless?

- Contingent Payment Clauses, Use With Caution

This article was originally posted on Express Lien’s topic-specific Construction Lien Blog.

Posted in:     Construction Contracts, Filing Requirements, Payment Requirements  /  Tags: , , , ,   /   1 Comment

Payment Provisions in Construction Contracts – Louisiana Law

Background on Payment Provisions & What is a “Pay When Paid” Clause

While it’s common practice in the construction industry to provide for partial payments from the contractor to subcontractor as work progresses, in Louisiana, unless the contract specifies otherwise, payment from the general contractor to the subcontractor is not actually due until the project is completed. See LA CC Art. 2550; See also Sacco v. Koepp, 169 La. 789, 793-94 (1930).

Therefore, if such progress payments are desired, it’s important to have a clause clearly providing for these payments in the contract.

A common contract provision in many contractor-subcontractor agreements provides that progress payments are not payable to a subcontractor until the owner pays the corresponding amount to the general contractor. These contract provisions typically come in two varieties, and are commonly referred to as “pay when paid” and “pay if paid” clauses.

“Pay when paid” and “Pay if paid” clauses are designed to shift the burden of owner non-payment from the contractor to its sub-contractors and suppliers. Accordingly, both provisions can be very onerous for the subcontractor – oftentimes preventing payments to a sub or supplier when the Owner is in an unrelated dispute with the general contractor, or merely becomes financially unable to make payments under the contract.

Enforceability of “Pay When Paid” Provisions

“Pay when Paid” provisions and other conditional payment provisions are not favored in courts, and therefore, it’s imperative to carefully draft and review any such provisions in the construction contract.

Hostility towards these types of provisions are fueled by subcontractors and their trade organizations.

Courts in some parts of the country have even gone so far as to call such provisions against public policy and unenforceable. See Capitol Steel Fabricators, Inc. v. Mega Construction Co., 58 Cal App 4th 1049 (2d Dist. 1997). Legislatures in a number of states have considered such provisions as impermissible waivers of the subcontractor’s constitutionally protected mechanics’ lien rights.

In Louisiana, properly drafted “Pay when Paid” provisions are enforceable, but the wording must be clear and unambiguous.

However, even with an enforceable conditional payment provision, Louisiana courts still require payment to the subcontractor within a “reasonable period of time,” thereby watering down the effect of the provision. See Southern States Masonry, Inc. v. J.A. Jones Contr. Co., 507 So.2d 198 (La. 1987). Through this Southern States decision, and similar decisions, the courts re-shift the risk of non-payment back upon the general contractor.

If the parties truly intend for the subcontractor to bear the risk of non-payment, or if payment from the owner is not reasonably certain, this intent should be clearly expressed in the construction contract. In these situations, the contract should have a “Pay if Paid” provision instead of a “Pay when Paid” provision. See C. Bel for Awnings, Inc. v. Blaine-Hays Constr. Co., 532 So.2d 830 (La. App. 4th Cir. 1988).

“Pay When Paid” versus “Pay If Paid”

Although only separated by one word, legally the two provisions are drastically different.

Pay when Paid

This common payment provision stipulates that a general contractor is legally obligated to pay a subcontractor only when it receives a corresponding payment from the owner. As discussed above, however, most courts view such a clause as a timing provision and not the basis for nonpayment.

Accordingly, if payment is never received from an owner, under a “Pay when Paid” payment provision, the general contractor must still make payment to a sub or supplier within a “reasonable time.”

Pay If Paid

“Pay if paid” clauses are more specific than their “pay when paid” counterparts. Unlike the “pay when paid” clause, oftentimes considered a timing provision, the “pay if paid” clause more clearly expresses the parties’ intention to shift the credit risk of owner nonpayment down through the contracting ranks.

Accordingly, payment to the subcontractor is more likely to be contingent on the general receiving payment from the owner under a contract with a “pay if paid” provision than a “pay when paid” provision.

Conclusion

Deciding when payments are due a subcontractor can sometimes lead to long and complicated legal disputes. As such, it’s very important for the parties to clearly express their intent when contracting.

The Wolfe Law Group is experienced in drafting and reviewing construction contracts to clearly reflect the intent of the parties. Contact us today to learn more about how the Wolfe Law Group can be your company’s new legal department.

Posted in:     Construction Contracts, Payment Requirements  /  Tags: , ,   /   Leave a comment